原帖由 slflkj 于 2007-7-6 14:08 发表
首先申明我不是高手.如有错误,请指正!
1.Correct ‘snatching’ should be incorporated to ensure that parts stay on correct half of
tool consistently during a production run.
1.模具在生产过程中 ...
唉,上头推的要命,可还有几句,用脚去想都是想不出来的 ,再请slflkj 出马帮帮忙啊!为了表示我的诚意,我愿意用我仅有的1分技作筹码!到时劳烦斑大帮帮忙了!
5.Bushings and/or ball cage bearings should be designed to remain captive during the forward and reverse ejection strokes.
6.16 way 16amp Harting plugs for the thermocouples, with the male side on the tool.
7.From 1 to 8 heaters - use 1 set of plugs
8.From 8 to 16 heaters - use 2 sets of plugs.
9.Hot-runner tools to be supplied fully wired. Ready to plug directly into Chilton power supply. Plugs to be fully secured to the top of tools.
10.Component and sprue should be dissimilar where possible to facilitate automatic sorting.
11.Cavities - where there are multiple cavities: these should be balanced correctly and numbered.
也麻烦帮我看看我翻译的几句:
12.Core pull cylinders to be hydraulic.
用水压来运行抽芯油缸.
13.For machines between 22 tonnes and 50 tonnes inclusive, ejector bars are to be fitted with ejector springs, which can be either on the ejector bar or on push-back pads. All tools for machines of 60 tonnes and over must have a clearance hole for a central ejector bar of 40mm diameter where possible, and a threaded hole of either 16mm or 20mm in the ejector plate to facilitate connection of the central ejector bar to the ejector plate. (See sketch “Ejection Standard” attached). Ref: Fig 3.
对于包括22T和50T或其之间的啤机,顶杆上是带有脱模弹弓的,弹弓可能装在顶杆上或者在限位块上.所有使用60T和60T以上的啤机的模具,必须要做一个直径为40MM的顶杆孔,并且要在顶针板上攻一个M16或M20的螺牙与顶杆相配.
14.Parts designed to eject into bin during automatic run must eject consistently.
把模具设计为在自动运行期间,产品被连续顶出,落入一个箱子里.
15.Ejector guide pillars to have oil grooves.
导柱处加油坑.
16.If possible, build tools so that they will sit on their own base when separated without the need for extra supports.
增加模脚使模具在分开时,模脚可独立支撑模体. |